Metsä Fibre is building a new Bio Product Mill in Kemi, Finland. The construction work started in 2021 and will be taken into use in 2023.
Metsä Fibre is building a new Bio Product Mill in Kemi, Finland. The construction work started in 2021 and will be taken into use in 2023.
° Detail Engineering, Procurement, Prefabrication and Installation of the HP-Piping
° Demanding HP-Piping
° High qualiinstallationty standard and strict requirements
° Short period
° Remote site location in Northern Finland, partly winter installation
° Global Covid 19 pandemic presence
° High prefabrication rate was used for shortening lead time and reducing needed manpower at site
° Recion’s own wide recourses in close internal co-operation
° Disciplines: power piping
° Lifespan: execution period 2022 – 2023
° Size: pipe weight approx. 200 tons